North River After the Fire: Project Controls Across Nine Contracts

Updated: Nov 4

Following the 2011 fire at North River, restoration work needed coordinated schedules, cost reporting, construction records, and consistent access to project information. Toll implemented the supporting Primavera-based system.

Client: New York City Department of Environmental Protection Location: Manhattan, New York Toll services: Primavera P6 and Contract Manager implementation; schedule and record structures; training; data QA/QC

AI-generated conceptual rendering of two professionals reviewing a construction schedule; not an actual North River project photograph.

Conceptual illustration of schedule and documentation coordination. AI-generated; not North River project personnel or an actual project record.

After a major plant fire, restoring a wastewater treatment facility requires more than repairs. Construction teams need to know which work is underway, which decisions remain open, and what the contract record actually says. Without a consistent information structure, the effort to reconstruct an operating facility can produce a second problem: fragmented project data.

That challenge shaped Toll International’s assignment on the North River Wastewater Treatment Plant Emergency Response Restoration and Reconstruction Project following the July 20, 2011 fire.

From emergency response to reconstruction

The fire damaged critical systems at North River, which serves Manhattan’s west side. NYC DEP organized the response in three phases: emergency response, restoration of plant operations, and reconstruction to full operational readiness. DEP and its contractors undertook the plant recovery; Toll’s documented assignment was to establish and administer the information tools used to manage the reconstruction program.

Across nine construction contracts, the project needed consistent scheduling, cost reporting, submittal tracking, and a way to retain decisions and daily activity records without relying on separate, disconnected files.

What Toll implemented

NYC DEP selected Toll to implement a project-controls system based on Oracle Primavera P6 and Contract Manager R14.1. The scope covered configuration of the scheduling and contract-management tools for construction schedules, cost reports, shop drawings, requests for information, drawings, meeting minutes, materials, and daily reports.

Toll also established user access and training for the construction manager, design engineer, and owner. To match DEP’s procedures and the specific needs of the North River work, the team customized Contract Manager with project-specific fields, dictionaries, and reporting structures.

Data quality was part of the assignment

A system cannot provide dependable visibility if the records inside it are incomplete or inconsistent. Toll performed ongoing quality assurance and quality control of data entered into the platform, a necessary discipline when many parties contribute to a shared project record.

The importance of that work is easy to overlook. A schedule activity, an unanswered RFI, an approved drawing revision, and a daily report may describe the same issue from different directions. A coordinated records environment helps the project team locate those relationships instead of reconstructing them after a dispute emerges.

The transferable capability

This was a project-controls implementation and support assignment, not a claim that Toll rebuilt the plant or performed the emergency restoration. The record supports a specific result: Toll established and customized P6- and Contract Manager-based processes to manage scheduling and construction documentation across nine contracts.

North River illustrates the role of structured project information when recovery, construction, and operational obligations overlap. The value lies in making the schedule, cost record, and field documentation usable together while decisions are still being made.

Project context sources

• Toll International — existing North River case study (https://www.tollintl.com/post/new-york-city-department-of-environmental-protection)

• NYC DEP — report on North River fire and restoration, September 19, 2011 (https://www.nyc.gov/html/dep/html/testimony/north_river_followup_09192011.shtml)

Comments


Contact us

(212) 920- 4115

​

​

 

​
 

tollinternational@tollintl.com

 

​
 

​

  • LinkedIn

Please reach out and hire us  or

apply for employment 

shield-keyhole.png

© 2026 by Toll International LLC. All rights reserved

bottom of page